Burien Pays Out $2.75 Million Over 1st Ave. S. Construction Project Overruns


Print This Post  Email This Post

by Ralph Nichols

All outstanding claims by contractors for cost overruns during phase one of the 1st Ave. S. improvement project have been settled by Burien for just under $3 million.

City Council members agreed to pay $2.75 million to resolve claims against Burien by general contractor Frank Coluccio Construction Co. and subcontractors Active Construction Inc. and Terra Dynamics (read the settlement here, p. 25 of PDF file).

The June 6 settlement was reached through two days of mediation, said Burien City Attorney Craig Knutson.

Coluccio and its subcontractors earlier filed suit in King County Superior Court to recover claims of more than $8 million for cost overruns resulting from delays, for which they held the city responsible.

An Aug. 1 trial date had been set in this case.

Active Construction did a lot of the trenching for undergrounding utilities. Terra Dynamics did landscaping work.

The city council also settled with Trans Tech Electric Inc. on April 4, agreeing to pay the subcontractor $177,902 and an additional $12,453 to Coluccio for the contractor’s markup for work performed.

Trans Tech, which installed street lighting and traffic signals, had filed a claim for $602,500.

Although “the city had a number of defenses we would have used at trial,” Knutson said Burien “would have been subject to pretrial interest [on the monetary claims] at 12 percent, and possibly [plaintiffs’] attorneys’ fees….

“Given the uncertainties of a jury trying to figure out a very complicated construction case,” coupled with a possibility the city “would have to pay a lot more” than the mediated agreement, settling contractors’ claims was reasonable, he told The B-Town Blog.

“I don’t know why they settled, but they faced the same uncertainties … and contractors don’t like to go to trial over construction claims.” Ninety-five percent of such claims are settled before a trial begins.

“Both sides had put a lot of effort into the case, but had not yet taken depositions” – which cost a lot in attorneys’ fees – “so both sides had a real incentive” to reach a pre-trial settlement through mediation,” Knutson added.

However, Burien expects “to recover a significant amount of this settlement” through payments from Seattle City Light and also Comcast, which are still being negotiated, for problems with their utility lines that contributed to construction delays.

Final cost of the project is approximately $26.4 million.

Phase one of the 1st Ave. S. rebuilding and redesign project between S/SW 162nd St. and S/SW 146th St. got underway on May 15, 2006, with completion scheduled for Nov. 27, 2007.

But repeated delays extended this project by almost a year. Construction finally ended – although utility undergrounding remains to be done, along with additional street lighting and curb, gutter and landscaping work – on Oct. 10, 2008.

Phase one planning took place while Gary Long was still Burien city manager, and Stephen Clark was public works director when the work was done.

As work fell behind schedule in 2007, Clark blamed it on bad weather the previous winter along with a cement processing strike – and utility conflicts and unanticipated problems encountered beneath the surface of 1st Ave.

Many businesses along the street reported heavy financial losses, with some going out of business as the result of construction.

Print This Post  Email This Post

Comments

6 Responses to “Burien Pays Out $2.75 Million Over 1st Ave. S. Construction Project Overruns”
  1. 3TreeCellars says:

    Something about the scheduled completion date of November 27, 2001 in paragraph 15 doesn’t make sense.

    Rate: Thumb up 0 Thumb down 0

  2. Get a clue burien city council says:

    And guess what, the ambaum repaving is over budget too

    Rate: Thumb up 0 Thumb down 0

  3. Burienite says:

    “Get a clue burien city council,” the Phase-1 1 st Avenue South project was bogged down with conflicts with Comcast and especially Seattle city light. Like the article mentioned, that phase isn’t even complete yet. There still is much work to be done to finish-out the project.

    Also, you can’t compare the Ambaum project with the 1st Avenue one. The Ambaum project is simply a sidewalk and asphalt overlay project. There is not trenching of utilities, etc.

    Rate: Thumb up 0 Thumb down 0

  4. Erik Robbins says:

    Do we have any idea when Phase 1 will be completed or started again?

    Rate: Thumb up 0 Thumb down 0

  5. Erik Robbins says:

    Quote from City of Burien’s agenda bill:

    “The Finance Department is proposing to use the General Fund to make the initial $1,000,000 payment and a line of
    credit from Key Bank to make the $1,750,000 payment. This will be followed by a bond issue that will fund the entire
    settlement and the unfunded part of the project. The City expects to receive reimbursement from Seattle City Light and
    Comcast for a substantial amount of the settlement that is allocated to utility and telecommunications work. If the City
    Council formally approves the settlement agreement, the reimbursement invoices will be sent to Seattle City Light and
    Comcast as soon as possible.”

    Can someone please explain the “Bond Issue” mentioned? Also, good luck getting any money from Comcast after reading the latest City Of Burien Survey on Comcast. That is going to be a very tough nut to crack.

    Rate: Thumb up 0 Thumb down 0

  6. Pete says:

    So yea, let’s move on and annex white center now…

    “Hello?, is this thing on?”

    Rate: Thumb up 0 Thumb down 0